Monday · November 16, 2026

 ·  Daily  ·  Newsletters

Resonance network: Quantum InsiderSpace Insider

Technology & Infrastructure · Data centres & compute

Nebius Plans $40B 2027 Spend as AI Data Centre Delays Test Microsoft Deal

Neocloud company Nebius has outlined $40 billion to $45 billion in planned capital spending for 2027, well above Wall Street expectations, while warning that delays at third-party sites are weighing on its AI infrastructure buildout.

CEO Arkady Volozh said building at this scale is hard and that Nebius is not immune to industry-wide delays. Capacity for Microsoft at a Vineland, New Jersey, site run by DataOne has slipped, with just over half now due by year-end and the rest in Q2 2027. Chief product and infrastructure officer Andrey Korolenko attributed the delay to DataOne winding down temporary generation faster than expected as it moves to Bloom Energy fuel cells. The contract, worth up to $19.4 billion, allows Microsoft to terminate affected service and impose penalties for missed dates, though Nebius said Microsoft has been part of the planning.

Chief revenue officer Marc Boroditsky said deals with Microsoft and Meta included large prepayments, and CFO Maria Del Dado Alonso Sanchez said prepayments and contract-backed financing should cover up to 85% of 2027 spending.

Nebius reported third-quarter revenue of $981 million, up 571%, but cut its 2026 forecast to $3 billion. It expects 2027 revenue of $12 billion to $13 billion. Shares fell 17%.

James Dargan
About the author
James Dargan

James Dargan is a writer and researcher at The AI Insider. His focus is on the AI startup ecosystem and he writes articles on the space that have a tone accessible to the average reader.

The AI economy, every weekday morning

The daily briefing plus the weekly Scale-ups to watch edition. Free, no spam, unsubscribe any time.